Power plant shutdown work protocol
POWER PLANT SHUTDOWN WORK PROTOCOL
DAMPER OVERHAULING WORKS |
||||||||||||
SN. |
LOCATION |
QUA-NTITY |
BEARING
CLEANING/ REPLACEMENT |
LINK ROD
CLEANING/REPLACEMENT |
DAMPER
FLAP REPAIR |
GEAR BOX
SERVICING |
LOCKING
ARRANGEMENT |
FLAP SAEL
CONDITION |
FINAL
TRIAL |
SPARES
USED |
REMARK |
|
1 |
RE – HEATER SUPER HEATER DAMPER |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
07 FLAPS |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE, M2 GREASE |
Stuffing box repaired, New gland replaced |
|
2 |
RE – HEATER DAMPER |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
08 FLAPS |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|
3 |
ESP INLET/OUTLET DAMPER |
16 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
- |
- |
- |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced, bearing
base plate painting done |
|
4 |
SECONDARY AIR DAMPER WIND BOX |
20 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|
5 |
APH INLET DAMPER COALD PA |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|
6 |
APH INLET
DAMPER SA |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|
7 |
APH INLET FLUE GAS DAMPER |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
- |
- |
- |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|
8 |
APH OUTLET DAMPER HOT PA |
02 |
1 BEARING
REPLACED AND OTHERS CLEANING DONE |
CLEANING WORK
DONE |
NOT APPLICABLE |
- |
FDLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE, BEARING F315 |
Stuffing box repaired, New gland replaced |
|
9 |
APH OUTLET DAMPER HOT SA |
02 |
ALL BEARING CLEANIG DONE |
CLEANING WORK
DONE |
NO NEED |
- |
FLAP GAP ADJUSTED |
OK |
YES |
12MM GALND ROPE |
Stuffing box repaired, New gland replaced |
|